Reduce labour·Increase capacity·Pay monthly·Prove the payback·UK-built warehouse automation·Get a monthly automation quote →·Finance options subject to specification & approval·Open the ROI engine →·Mechanical · electrical · controls · WCS · support, one UK facility·New guide: what warehouse automation costs — read here →·Cross-belt vs tilt-tray vs wheel sorters — read here →·
Helix Helios ROI Finance Products Case studies News & builds Send a sketch Solution builder FAQs Book a site visit
← All insights
Insights · Installation & planning · 24 Aug 2026

How long does warehouse automation take to install?

The honest UK answer: smaller conveyor packages typically take 6–10 weeks from order to arriving on site. A full Helix sortation system runs 12–25 weeks order-to-live, with the detailed programme confirmed at Functional Design Specification stage. And the part most buyers overestimate — the on-site installation itself — typically completes in under 4 weeks, because the system is built and tested at the factory before it ships.

This guide walks through every phase, what stretches a programme, what compresses one, and the calendar maths for hitting peak.

UK timelines · at a glance

Order to live, in numbers

  • Conveyor packages, to site6–10 weeks
  • Full Helix sortation, to live12–25 weeks
  • Typical on-site install< 4 weeks
  • Amazon pick tower install3 days
  • QC cell, order to on-site3 weeks

Detailed programmes confirmed at FDS stage

The short answer

Smaller conveyor packages typically take 6–10 weeks from order to arriving on site. A full sortation system takes 12–25 weeks from order to live operation, and the on-site installation phase within that typically completes in under 4 weeks. The detailed programme for any system is confirmed at Functional Design Specification stage, once scope, parcel profile and integration are pinned down. No building extensions or planning permission are required — Orion systems are designed to fit the building you already have.

Those ranges surprise people in both directions. Buyers who have heard horror stories of year-long automation programmes are surprised how short the whole thing is; buyers who imagine a conveyor arriving next week are surprised it takes six. The difference comes from understanding where the time actually goes — which is mostly not on your site.

What happens in each phase

Every Orion programme, from a single conveyor spur to a full Helix sortation system, moves through the same sequence. What varies is how long each phase takes and how many run in parallel.

1. Functional Design Specification (FDS)

The FDS is where the system stops being a proposal and becomes an engineering document: throughput rates, parcel or product profile, layout drawings, control philosophy, integration points with your WMS, and the programme itself. This is the stage where the detailed timeline is confirmed — because until scope is fixed, any date is a guess. Getting your data ready early (volumes by hour, item dimensions and weights, site drawings) is the single cheapest way to keep this phase short.

2. Design and engineering

Mechanical design, electrical design, PLC control code and WCS configuration all happen in-house at Orion's Chichester facility. That matters for the programme: there is no waiting on a controls subcontractor's lead time or a design house's queue. Mechanical and electrical design typically run in parallel, and long-lead purchased items — drives, gearboxes, safety components — are ordered as soon as the design freezes them.

3. Manufacture and factory pre-build

Frames are fabricated, conveyors built, and — critically — the system is assembled and run at the factory before it ships. Pre-build and test is the quiet hero of a short programme: control faults, mechanical snags and software issues get found and fixed in the factory, where fixing them costs hours, rather than on your site, where fixing them costs days of your operation. This phase is usually the longest single block in the programme, and it is entirely invisible to your warehouse.

4. Delivery and mechanical installation

The system arrives in pre-built, pre-tested sections and is positioned, levelled and bolted together. Because the hard assembly work happened at the factory, site mechanical work is reassembly, not construction — which is why a typical Helix on-site installation completes in under 4 weeks, and smaller packages in days.

5. Electrical installation and controls

Power distribution, field wiring, sensors and safety circuits are connected and point-to-point tested. The PLC code and WCS arriving on site have already run the system once at the factory, so this phase is verification, not development.

6. Commissioning and handover

The system runs first empty, then with live product, ramping to rate. Operators and engineering staff are trained on the machine, documentation is handed over, and the system passes to support. On a well-run programme, commissioning confirms what the factory test already proved.

What stretches a timeline

What compresses one: pre-build and test

The single biggest compression lever is doing the work before the system ever reaches site. Because Orion designs, fabricates, wires and codes everything in one UK facility, systems ship as tested assemblies — and the on-site record shows what that makes possible:

Orion pick tower installed inside a live Amazon fulfilment centre
Amazon pick tower — installed and commissioned in 3 days, without stopping the building.

These are not typical programme lengths for full systems — a sortation system will still take its 12–25 weeks order-to-live — but they show where the time in that programme sits. It sits in design and manufacture, off your site, while your operation runs untouched. The disruptive part at the end is short because everything difficult was already done.

Installing into a live operation without stopping it

Most UK warehouses cannot shut down for an installation, and with the right method they do not have to. The Gompels line was installed with zero downtime to the existing operation. The BMW kitting line was introduced into live production without stopping it — sequenced around shift patterns, with the new line built alongside the running process and cut over when proven. The Amazon pick tower went into a building that never stopped shipping.

The method is consistent: pre-built sections arrive ready to position, installation work is sequenced into windows the operation can give (nights, weekends, quiet shifts where needed), and the cutover happens only when the new equipment has already demonstrated it works. In food environments the same discipline applies harder still — the Tate & Lyle sugar-line conveyors serve a continuous 24/7 operation with zero permitted downtime, which shapes every hour of the installation plan.

It also helps that nothing about the building has to change. Orion systems fit inside existing structures — no building extensions, no planning permission, no landlord negotiations adding months to the front of the programme.

The peak-season calendar maths

For UK e-commerce, 3PL and parcel operations, the question behind the question is usually: can it be running before peak? Work the dates backwards from November and the answer writes itself.

A smaller conveyor package on a 6–10 week programme, ordered in late August, is typically running by early November — installed, commissioned and settled in before peak volumes arrive. That is the comfortable version of the timeline, with weeks in hand for the operation to get used to the new line.

Leave the decision until autumn and the same maths turns against you: the machine you order in October arrives in the new year. It will still be a good machine — it just spends peak as a purchase order while your team spends peak on overtime and agency rates. The guide to the real cost of manual sortation puts numbers on exactly what that costs at £16.30/hr all-in.

Full sortation systems need the decision earlier still. At 12–25 weeks order-to-live, a Helix system intended to be sorting before Christmas needs its order placed in spring or early summer, with the FDS signed off promptly behind it. If you are reading this in autumn with peak already looming, the honest advice is to talk about next year's peak now — and let this year's numbers make the case.

What this means for your decision

Installation time is rarely the reason to delay automation — the programme is shorter than most buyers expect, the disruptive portion is measured in days or weeks rather than months, and the cost of waiting is a full peak season of manual labour. The commercial side of the decision is covered in what warehouse automation costs in the UK, and everything is available on monthly finance from around £4,000 per month on a 60-month term, subject to specification and approval — so the system can start paying for itself from the month it goes live.

Whether you run a parcel centre, a 3PL, a fulfilment operation or a food manufacturing site, the sequence is the same — and the ROI calculator will tell you what the machine earns while you wait for it.

FAQs

Install timelines, asked directly.

How long does a conveyor system take to install in the UK?

Smaller Orion conveyor packages typically take 6–10 weeks from order to arriving on site, because design, fabrication and controls all happen in-house at one UK facility. On-site installation for a package of that size is usually measured in days rather than weeks — one plug-and-play QC automation cell went from order to on-site in 3 weeks and commissioned with zero snags.

How long does a full sortation system take from order to live?

A full Helix sortation system typically runs 12–25 weeks order-to-live, with the detailed programme confirmed at Functional Design Specification stage. Most of that time is off-site design and manufacture — the on-site installation itself typically completes in under 4 weeks because the system is pre-built and tested at the factory before delivery.

Do I need planning permission or a building extension for warehouse automation?

No. Orion systems are designed to fit inside your existing building — no building extensions and no planning permission are required. Conveyor lines and Helix sortation follow the building you already have, running along walls, down spines and between dock doors, which is one reason on-site programmes stay short.

When do I need to order automation to be running before Christmas peak?

For a conveyor package on a 6–10 week programme, an order placed in late August is typically running by early November — before peak volumes hit. Leave it later and the maths turns against you: the machine you order in October arrives in the new year. Full sortation systems at 12–25 weeks order-to-live need a decision in spring or early summer to be live for the same peak.

Next step

Want a real programme, not a range?

Send your volumes, layout and go-live target. We'll come back with a phased programme — FDS to handover — and an indicative monthly figure to sit alongside it.

Timelines are typical ranges; detailed programmes are confirmed at Functional Design Specification stage. Finance options available subject to specification and approval.